Topic 1- Permit Approval Documentation

Results of public hearings are not formalized until after the appeal period’s expiration and another meeting of the commission or board when previous meeting minutes can be approved by a majority vote, signed by the board or commission chair, and sealed by the secretary. Some jurisdictions require a reading of each approval at the city council for up to three meetings before the approval becomes final. Wireless site operators require the site acquisition consultant to collect and submit all approval documentation for project files before final project compensation is disbursed.